DAFTAR ANALISA PEKERJAAN | ||||||||||||
SNI.DT 91-0012-2007 | ||||||||||||
PEKERJAAN PENUTUP LANTAI DAN DINDING | ||||||||||||
SNI.DT 91-0012-2007.6.13 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (60x60) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik 60x60 | Bh | 3.100 | Rp. | 45,000.00 | Rp. | Rp. | 139,500.00 | Rp. | |||
Portland cement | kg | 9.600 | Rp. | 1,100.00 | Rp. | Rp. | 10,560.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.500 | Rp. | 3,075.00 | Rp. | Rp. | 4,612.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.240 | Rp. | Rp. | Rp. | Rp. | 0.00 | ||||
Tukang Batu | Oh | 0.120 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 8,640.00 | ||||
Kepala Tukang | Oh | 0.012 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 960.00 | ||||
Mandor | Oh | 0.012 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 864.00 | ||||
158,722.50 | 10,464.00 | |||||||||||
Jumlah harga = | Rp. | 169,186.50 | ||||||||||
Pembulatan = | Rp. | 169,190.00 | ||||||||||
SNI.DT 91-0012-2007.6.34 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (40x40) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 6.500 | Rp. | 8,833.33 | Rp. | Rp. | 57,416.65 | Rp. | |||
Portland cement | kg | 8.190 | Rp. | 1,100.00 | Rp. | Rp. | 9,009.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | Rp. | Rp. | 0.00 | ||||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
75,457.15 | 30,520.00 | |||||||||||
Jumlah harga = | Rp. | 105,977.15 | ||||||||||
Pembulatan = | Rp. | 105,980.00 | ||||||||||
SNI.DT 91-0012-2007.6.35 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (30x30) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 11.500 | Rp. | 4,909.09 | Rp. | Rp. | 56,454.54 | Rp. | |||
Portland cement | kg | 10.000 | Rp. | 1,100.00 | Rp. | Rp. | 11,000.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.500 | Rp. | 3,075.00 | Rp. | Rp. | 4,612.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
76,117.04 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 141,637.04 | ||||||||||
Pembulatan = | Rp. | 141,640.00 | ||||||||||
SNI.DT 91-0012-2007.6.36 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (20x20) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 25.000 | Rp. | 1,960.00 | Rp. | Rp. | 49,000.00 | Rp. | |||
Portland cement | kg | 10.400 | Rp. | 1,100.00 | Rp. | Rp. | 11,440.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
69,471.50 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 134,991.50 | ||||||||||
Pembulatan = | Rp. | 134,990.00 | ||||||||||
SNI.DT 91-0012-2007.6.36.1 | ||||||||||||
Memasang 1 m2 dinding keramik ukuran (20x25) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 20.000 | Rp. | 2,250.00 | Rp. | Rp. | 45,000.00 | Rp. | |||
Portland cement | kg | 10.400 | Rp. | 1,100.00 | Rp. | Rp. | 11,440.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
65,471.50 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 130,991.50 | ||||||||||
Pembulatan = | Rp. | 130,990.00 | ||||||||||
SNI.DT 91-0012-2007.6.44 | ||||||||||||
Memasang 1 m2 lantai karpet | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Karpet | m2 | 1.050 | Rp. | 36,000.00 | Rp. | Rp. | 37,800.00 | Rp. | |||
Lem | kg | 0.350 | Rp. | 45,000.00 | Rp. | Rp. | 15,750.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.170 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 8,500.00 | |||
Tukang Kayu | Oh | 0.170 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 12,240.00 | ||||
Kepala Tukang | Oh | 0.017 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 1,360.00 | ||||
Mandor | Oh | 0.009 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 648.00 | ||||
53,550.00 | 22,748.00 | |||||||||||
Jumlah harga = | Rp. | 76,298.00 | ||||||||||
Pembulatan = | Rp. | 76,300.00 | ||||||||||
SNI.DT 91-0012-2007.6.46 | ||||||||||||
Memasang 1 m2 lantai parquet | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Parquet | m2 | 1.050 | Rp. | 270,000.00 | Rp. | Rp. | 283,500.00 | Rp. | |||
Lem | kg | 0.600 | Rp. | 45,000.00 | Rp. | Rp. | 27,000.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
310,500.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 376,020.00 | ||||||||||
Pembulatan = | Rp. | 376,020.00 | ||||||||||
SNI.DT 91-0012-2007.6.47 | ||||||||||||
Memasang 1 m2 lantai kayu (gym floor) | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Gymfloor | m2 | 1.050 | Rp. | 180,000.00 | Rp. | Rp. | 189,000.00 | Rp. | |||
Lem | kg | 0.600 | Rp. | 45,000.00 | Rp. | Rp. | 27,000.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
216,000.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 281,520.00 | ||||||||||
Pembulatan = | Rp. | 281,520.00 | ||||||||||
SNI.DT 91-0012-2007.6.57 | ||||||||||||
Memasang 1 m2 dinding batu paras | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Batu paras | m2 | 1.100 | Rp. | 180,000.00 | Rp. | Rp. | 198,000.00 | Rp. | |||
Potrland cement | kg | 11.750 | Rp. | 1,100.00 | Rp. | Rp. | 12,925.00 | Rp. | ||||
Pasir pasang | m3 | 0.035 | Rp. | 90,000.00 | Rp. | Rp. | 3,150.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang batu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
214,075.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 279,595.00 | ||||||||||
Pembulatan = | Rp. | 279,600.00 | ||||||||||
SNI.DT 91-0012-2007.6.58 | ||||||||||||
Memasang 1 m2 dinding batu tempel hitam | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Batu tempel hitam | m2 | 1.100 | Rp. | 135,000.00 | Rp. | Rp. | 148,500.00 | Rp. | |||
Potrland cement | kg | 11.750 | Rp. | 1,100.00 | Rp. | Rp. | 12,925.00 | Rp. | ||||
Pasir pasang | m3 | 0.035 | Rp. | 90,000.00 | Rp. | Rp. | 3,150.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang batu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
164,575.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 230,095.00 | ||||||||||
Pembulatan = | Rp. | 230,100.00 | ||||||||||
SNI.DT 91-0012-2007.6.60 | ||||||||||||
Memasang 1 m2 wall paper | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Wallpaper | m2 | 2.200 | Rp. | 94,000.00 | Rp. | Rp. | 206,800.00 | Rp. | |||
Lem | kg | 0.250 | Rp. | 45,000.00 | Rp. | Rp. | 11,250.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.350 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 17,500.00 | |||
Tukang | Oh | 0.175 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 12,600.00 | ||||
Kepala Tukang | Oh | 0.017 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 1,360.00 | ||||
Mandor | Oh | 0.002 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 144.00 | ||||
218,050.00 | 31,604.00 | |||||||||||
Jumlah harga = | Rp. | 249,654.00 | ||||||||||
Pembulatan = | Rp. | 249,650.00 | ||||||||||
SNI.DT 91-0012-2007.6.61 | ||||||||||||
Memasang 1 m2 floor hardener | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Floor Hardener | kg | 5.000 | Rp. | 3,500.00 | Rp. | Rp. | 17,500.00 | Rp. | |||
Tenaga | Pekerja | Oh | 0.120 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 6,000.00 | |||
Tukang | Oh | 0.120 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 8,640.00 | ||||
Kepala Tukang | Oh | 0.012 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 960.00 | ||||
Mandor | Oh | 0.006 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 432.00 | ||||
17,500.00 | 16,032.00 | |||||||||||
Jumlah harga = | Rp. | 33,532.00 | ||||||||||
Pembulatan = | Rp. | 33,530.00 | ||||||||||
SNI.DT 91-0012-2007.6.7 | ||||||||||||
Memasang 1 m2 conblok #6 cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Conblok #6cm | bh | 44.000 | Rp. | 1,800.00 | Rp. | Rp. | 79,200.00 | Rp. | |||
Pasir urug | m3 | 0.055 | Rp. | 73,000.00 | Rp. | Rp. | 4,015.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.300 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 15,000.00 | |||
Tukang | Oh | 0.200 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 14,400.00 | ||||
Kepala Tukang | Oh | 0.010 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 800.00 | ||||
Mandor | Oh | 0.010 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 720.00 | ||||
83,215.00 | 30,920.00 | |||||||||||
Jumlah harga = | Rp. | 114,135.00 | ||||||||||
Pembulatan = | Rp. | 114,140.00 | ||||||||||
Home » Tanpa Label » DAFTAR ANALISA PEKERJAAN SNI.DT 91-0012-2007 PEKERJAAN PENUTUP LANTAI DAN DINDING
DAFTAR ANALISA PEKERJAAN | ||||||||||||
SNI.DT 91-0012-2007 | ||||||||||||
PEKERJAAN PENUTUP LANTAI DAN DINDING | ||||||||||||
SNI.DT 91-0012-2007.6.13 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (60x60) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik 60x60 | Bh | 3.100 | Rp. | 45,000.00 | Rp. | Rp. | 139,500.00 | Rp. | |||
Portland cement | kg | 9.600 | Rp. | 1,100.00 | Rp. | Rp. | 10,560.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.500 | Rp. | 3,075.00 | Rp. | Rp. | 4,612.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.240 | Rp. | Rp. | Rp. | Rp. | 0.00 | ||||
Tukang Batu | Oh | 0.120 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 8,640.00 | ||||
Kepala Tukang | Oh | 0.012 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 960.00 | ||||
Mandor | Oh | 0.012 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 864.00 | ||||
158,722.50 | 10,464.00 | |||||||||||
Jumlah harga = | Rp. | 169,186.50 | ||||||||||
Pembulatan = | Rp. | 169,190.00 | ||||||||||
SNI.DT 91-0012-2007.6.34 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (40x40) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 6.500 | Rp. | 8,833.33 | Rp. | Rp. | 57,416.65 | Rp. | |||
Portland cement | kg | 8.190 | Rp. | 1,100.00 | Rp. | Rp. | 9,009.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | Rp. | Rp. | 0.00 | ||||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
75,457.15 | 30,520.00 | |||||||||||
Jumlah harga = | Rp. | 105,977.15 | ||||||||||
Pembulatan = | Rp. | 105,980.00 | ||||||||||
SNI.DT 91-0012-2007.6.35 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (30x30) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 11.500 | Rp. | 4,909.09 | Rp. | Rp. | 56,454.54 | Rp. | |||
Portland cement | kg | 10.000 | Rp. | 1,100.00 | Rp. | Rp. | 11,000.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.500 | Rp. | 3,075.00 | Rp. | Rp. | 4,612.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
76,117.04 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 141,637.04 | ||||||||||
Pembulatan = | Rp. | 141,640.00 | ||||||||||
SNI.DT 91-0012-2007.6.36 | ||||||||||||
Memasang 1 m2 lantai keramik ukuran (20x20) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 25.000 | Rp. | 1,960.00 | Rp. | Rp. | 49,000.00 | Rp. | |||
Portland cement | kg | 10.400 | Rp. | 1,100.00 | Rp. | Rp. | 11,440.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
69,471.50 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 134,991.50 | ||||||||||
Pembulatan = | Rp. | 134,990.00 | ||||||||||
SNI.DT 91-0012-2007.6.36.1 | ||||||||||||
Memasang 1 m2 dinding keramik ukuran (20x25) cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Lantai keramik | Bh | 20.000 | Rp. | 2,250.00 | Rp. | Rp. | 45,000.00 | Rp. | |||
Portland cement | kg | 10.400 | Rp. | 1,100.00 | Rp. | Rp. | 11,440.00 | Rp. | ||||
Pasir pasang | m3 | 0.045 | Rp. | 90,000.00 | Rp. | Rp. | 4,050.00 | Rp. | ||||
Semen warna | kg | 1.620 | Rp. | 3,075.00 | Rp. | Rp. | 4,981.50 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
65,471.50 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 130,991.50 | ||||||||||
Pembulatan = | Rp. | 130,990.00 | ||||||||||
SNI.DT 91-0012-2007.6.44 | ||||||||||||
Memasang 1 m2 lantai karpet | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Karpet | m2 | 1.050 | Rp. | 36,000.00 | Rp. | Rp. | 37,800.00 | Rp. | |||
Lem | kg | 0.350 | Rp. | 45,000.00 | Rp. | Rp. | 15,750.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.170 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 8,500.00 | |||
Tukang Kayu | Oh | 0.170 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 12,240.00 | ||||
Kepala Tukang | Oh | 0.017 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 1,360.00 | ||||
Mandor | Oh | 0.009 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 648.00 | ||||
53,550.00 | 22,748.00 | |||||||||||
Jumlah harga = | Rp. | 76,298.00 | ||||||||||
Pembulatan = | Rp. | 76,300.00 | ||||||||||
SNI.DT 91-0012-2007.6.46 | ||||||||||||
Memasang 1 m2 lantai parquet | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Parquet | m2 | 1.050 | Rp. | 270,000.00 | Rp. | Rp. | 283,500.00 | Rp. | |||
Lem | kg | 0.600 | Rp. | 45,000.00 | Rp. | Rp. | 27,000.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
310,500.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 376,020.00 | ||||||||||
Pembulatan = | Rp. | 376,020.00 | ||||||||||
SNI.DT 91-0012-2007.6.47 | ||||||||||||
Memasang 1 m2 lantai kayu (gym floor) | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Gymfloor | m2 | 1.050 | Rp. | 180,000.00 | Rp. | Rp. | 189,000.00 | Rp. | |||
Lem | kg | 0.600 | Rp. | 45,000.00 | Rp. | Rp. | 27,000.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang Kayu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
216,000.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 281,520.00 | ||||||||||
Pembulatan = | Rp. | 281,520.00 | ||||||||||
SNI.DT 91-0012-2007.6.57 | ||||||||||||
Memasang 1 m2 dinding batu paras | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Batu paras | m2 | 1.100 | Rp. | 180,000.00 | Rp. | Rp. | 198,000.00 | Rp. | |||
Potrland cement | kg | 11.750 | Rp. | 1,100.00 | Rp. | Rp. | 12,925.00 | Rp. | ||||
Pasir pasang | m3 | 0.035 | Rp. | 90,000.00 | Rp. | Rp. | 3,150.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang batu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
214,075.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 279,595.00 | ||||||||||
Pembulatan = | Rp. | 279,600.00 | ||||||||||
SNI.DT 91-0012-2007.6.58 | ||||||||||||
Memasang 1 m2 dinding batu tempel hitam | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Batu tempel hitam | m2 | 1.100 | Rp. | 135,000.00 | Rp. | Rp. | 148,500.00 | Rp. | |||
Potrland cement | kg | 11.750 | Rp. | 1,100.00 | Rp. | Rp. | 12,925.00 | Rp. | ||||
Pasir pasang | m3 | 0.035 | Rp. | 90,000.00 | Rp. | Rp. | 3,150.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.700 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 35,000.00 | |||
Tukang batu | Oh | 0.350 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 25,200.00 | ||||
Kepala Tukang | Oh | 0.035 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 2,800.00 | ||||
Mandor | Oh | 0.035 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 2,520.00 | ||||
164,575.00 | 65,520.00 | |||||||||||
Jumlah harga = | Rp. | 230,095.00 | ||||||||||
Pembulatan = | Rp. | 230,100.00 | ||||||||||
SNI.DT 91-0012-2007.6.60 | ||||||||||||
Memasang 1 m2 wall paper | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Wallpaper | m2 | 2.200 | Rp. | 94,000.00 | Rp. | Rp. | 206,800.00 | Rp. | |||
Lem | kg | 0.250 | Rp. | 45,000.00 | Rp. | Rp. | 11,250.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.350 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 17,500.00 | |||
Tukang | Oh | 0.175 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 12,600.00 | ||||
Kepala Tukang | Oh | 0.017 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 1,360.00 | ||||
Mandor | Oh | 0.002 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 144.00 | ||||
218,050.00 | 31,604.00 | |||||||||||
Jumlah harga = | Rp. | 249,654.00 | ||||||||||
Pembulatan = | Rp. | 249,650.00 | ||||||||||
SNI.DT 91-0012-2007.6.61 | ||||||||||||
Memasang 1 m2 floor hardener | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Floor Hardener | kg | 5.000 | Rp. | 3,500.00 | Rp. | Rp. | 17,500.00 | Rp. | |||
Tenaga | Pekerja | Oh | 0.120 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 6,000.00 | |||
Tukang | Oh | 0.120 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 8,640.00 | ||||
Kepala Tukang | Oh | 0.012 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 960.00 | ||||
Mandor | Oh | 0.006 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 432.00 | ||||
17,500.00 | 16,032.00 | |||||||||||
Jumlah harga = | Rp. | 33,532.00 | ||||||||||
Pembulatan = | Rp. | 33,530.00 | ||||||||||
SNI.DT 91-0012-2007.6.7 | ||||||||||||
Memasang 1 m2 conblok #6 cm | ||||||||||||
Kebutuhan | Satuan | Indeks | Harga satuan | Harga satuan | Jumlah harga bahan | Jumlah harga upah | ||||||
Bahan | Conblok #6cm | bh | 44.000 | Rp. | 1,800.00 | Rp. | Rp. | 79,200.00 | Rp. | |||
Pasir urug | m3 | 0.055 | Rp. | 73,000.00 | Rp. | Rp. | 4,015.00 | Rp. | ||||
Tenaga | Pekerja | Oh | 0.300 | Rp. | Rp. | 50,000.00 | Rp. | Rp. | 15,000.00 | |||
Tukang | Oh | 0.200 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 14,400.00 | ||||
Kepala Tukang | Oh | 0.010 | Rp. | Rp. | 80,000.00 | Rp. | Rp. | 800.00 | ||||
Mandor | Oh | 0.010 | Rp. | Rp. | 72,000.00 | Rp. | Rp. | 720.00 | ||||
83,215.00 | 30,920.00 | |||||||||||
Jumlah harga = | Rp. | 114,135.00 | ||||||||||
Pembulatan = | Rp. | 114,140.00 | ||||||||||
Previous
PadangsidimpuanRELATED POSTS
Uji konsistensi Data Hujan, Memperkirakan Data Hujan yang Hilang dan Memperkirakan Data Hujan Wilayah Uji konsistensi Data HujanSiklus hidrologi adalah perputaran air dengan perubahan berbagai bentuk dan kembali pada bentuk a…
Daur Siklus Dan Tahapan Proses Siklus HidrologiDaur Siklus HidrologiSiklus hidrologi adalah perputaran air dengan perubahan berbagai bentuk dan kembali pada bentuk awal. Hal ini…
Uji Parameter Kekuatan Geser Tanah di Laboratorium : Uji Tiga Paksi (Triaxial Test)…
Uji Parameter Kekuatan Geser Tanah di Laboratorium : Uji Geser Langsung (Direct Shear Test)…
Distribusi Ukuran Butiran (Grain Size Analysis)- Distribusi Ukuran Butiran (Grain Size Analysis)Distribusi ukuran butiran adalah penentuan persentase berat butiran pada satu uni…
3 Comment for "DAFTAR ANALISA PEKERJAAN SNI.DT 91-0012-2007 PEKERJAAN PENUTUP LANTAI DAN DINDING"
Terima kasih infonya gan.
Lumayan buat nambah elmu.
Spam Detected! Link aktif otomatis terhapus!!!
Spam Detected! Link aktif otomatis terhapus!!!
----------
klo untk keramik 30x60 gimana ya bos? Thanks
thanks gan infomasinya sangat berguna, kunjungi juga http://www.ahlibeton.co.id/2015/09/floor-hardener.html untuk pembuatan floorhardener